The budget available for a bridge that a few farmers use is likely laughable.
$1:
According to Sasktenders, the bridge contract was worth $325,000. Hicks said it's difficult to justify a huge budget for this bridge, which he estimated would have about 1,000 vehicles crossing it annually.
$1:
He said the issue was with five underwater pilings and "the whole five of them just went straight down. Boom. Four feet."
"So something tells me that something underneath the ground happened. I don't know what it was. They don't know what it was. Nobody knows what it is."
$1:
"I think it's irregular that a proper geotechnical program wasn't done for the piers in the water," said Gauvreau, an engineering professor at the U of T. "And it is not correct to say that it can't be done in a river. It's done all the time."
https://www.cbc.ca/news/canada/saskatch ... -1.4829890Now that geotechnical review doesn't look so expensive, compared to fixing the problem, hmmmm?
As the saying goes, "if you don't have the budget to do it right, how will you find the budget to do it over?"